Recently Concluded Procurements
The following is a list of recently completed procurements:
Request For Renewable Energy Certificates
April 22, 2024
For Calendar Years:
Rhode Island
2023 & 2024
The Narragansett Electric Company ("Narragansett") has issued a Request for Proposals to purchase Renewable Energy Certificates (RECs) to meet the Rhode Island Renewable Energy Standard (RES). Narragansett is seeking proposals for the supply of RECs from generating facilities in Rhode Island, New England and surrounding regions that have been approved by the Rhode Island Public Utilities Commission as existing renewable energy resources that meet the RES requirements. The following table summarizes the quantity of certificates Narragansett is seeking:
Year
NEPOOL-GIS Certificates from Existing Energy Resources
NEPOOL-GIS Certificates from New Energy Resources
Total NEPOOL-GIS Certificates
2023
6,060
0
6,060
2024
30,000
0
30,000
Respondent Information and Proposed Contract Modifications Due
April 25, 2024 @
5pm EST
Respondent Pricing Due
April 26, 2024 @
10am EST
Request for Proposal (pdf)
Request For Power Supply Proposals
March 8, 2024
For the Periods:
Rhode Island
July 1, 2024 to September 30, 2025
The Narragansett Electric Company has issued a Request for Proposals to serve the following customer group(s):
Rhode Island Last Resort Service Residential Customer Group
October 1, 2024 to September 30, 2025 (20% of load)
Rhode Island
Last Resort Service Commercial Customer Group:
October 1, 2024 to September 30, 2025 (20% of load)
Rhode Island
Last Resort Service Industrial Customer Group:
July 1, 2024 to September 30, 2024 (100% of load)
In Rhode Island, The Narragansett Electric Company ("Narragansett") is seeking fixed price bids for load following service to meet its Last Resort Service for the Residential Group, the Commercial Group, and the Industrial Group. Narragansett intends to evaluate and select supplier(s) on the same day that final pricing is due. Narragansett reserves the right to award all or none of the blocks in the RFP.
Respondent Proposal Information Due
March 22, 2024 -
5pm EPT
Indicative Pricing Due
April 3, 2024 - 10am EPT
Final Pricing Due
April 10, 2024 - 10am EPT
Request for Proposal (pdf)
Request For Power Supply Proposals
February 9, 2024
For the Periods:
Massachusetts
May 1, 2024 to July 31, 2024 .
Massachusetts Electric Company and Nantucket Electric Company ("Companies") have issued a Request for Proposals to serve the following customer group:
Massachusetts Industrial Customer Basic Service:
May 1, 2024 to July 31, 2024 (100% of load)
Massachusetts Electric Company and Nantucket Electric Company ("Companies") have issued a Request for Proposals seeking fixed price bids for load following service for the Industrial Customer Group in each of the three load zones (SEMA, NEMA, and WCMA). The Companies intend to evaluate and select supplier(s) on the same day that final pricing is due.
Respondent Proposal Information and Proposed Contract Modifications Due
February 23, 2024 -
5pm EPT
Indicative Pricing Due
March 6, 2024 - 10am EPT
Final Pricing Due
March 13, 2024- 10am EPT
Request for Proposal (pdf)
Request For Proposals for Renewable Energy Certificates
February 29, 2024
For Calendar Years:
Massachusetts
2023
2024
The Massachusetts Electric Company and Nantucket Electric Company have issued a Request for Proposals to purchase certificates to meet the Massachusetts Renewable Energy Portfolio Standard ("RPS"), the Alternative Energy Portfolio Standard ("APS"), the Clean Peak Energy Portfolio Standard ("CPS") and the Clean Energy Standard ("CES"). The Massachusetts Electric Company and the Nantucket Electric Company are seeking proposals for the supply of certificates from generating facilities in Massachusetts, New England and surrounding regions that have been approved by the Massachusetts Department of Energy Resources as Class I new renewable energy resources, Class I Solar Carve-Out new renewable energy resources, Class I Solar Carve-Out II new renewable energy resources, Class II existing renewable energy resources and Class II Waste Energy existing renewable resources that meet the RPS requirements. The companies are also seeking proposals for certificates that meet the APS, CPS, and CES-E requirements. The following tables summarize the quantity of certificates the companies are seeking:
Year
MA RPS Qualified NEPOOL GIS Certificates(Class I)
MA RPS Qualified NEPOOL GIS Certificates (Class I Solar Carve-Out)
MA RPS Qualified NEPOOL GIS Certificates (Class I Solar Carve-Out II)
MA RPS Qualified NEPOOL GIS Certificates(Class II)
MA RPS Qualified NEPOOL GIS Certificates(Class II-Waste Energy)
MA APS Qualified NEPOOL GIS Certificates(AEC)
2023
0
4,000
4,000
0
0
0
2024
0
0
20,000
25,000
25,000
50,000
Year
MA CES Qualified NEPOOL GIS Certificates(CES-E)
MA CPS Qualified NEPOOL GIS Certificates (CPEC)
2023
200,000
50,000
2024
300,000
75,000
Respondent Proposal Information and Pricing Due
March 6, 2024 @
12pm EPT
Company Reviews Pricing and Informs Winning Respondents
March 8, 2024 @
5pm EPT
Request for Proposal (pdf)
Proposed Massachusetts Master Power Agreement (doc)
Required Proposal Information (.doc)
Pricing Submission Form (.xls)
Contacts:
Kris Hornberger
Wholesale Electric Supply
National Grid [email protected]
(email)
Request For Proposals for Renewable Energy Certificates
November 29, 2023
For Calendar Years:
Massachusetts
2023
2024
The Massachusetts Electric Company and Nantucket Electric Company have issued a Request for Proposals to purchase certificates to meet the Massachusetts Renewable Energy Portfolio Standard (�RPS�), the Alternative Energy Portfolio Standard (�APS�), the Clean Peak Energy Portfolio Standard (�CPS�) and the Clean Energy Standard (�CES�). The Massachusetts Electric Company and the Nantucket Electric Company are seeking proposals for the supply of certificates from generating facilities in Massachusetts, New England and surrounding regions that have been approved by the Massachusetts Department of Energy Resources as Class I new renewable energy resources, Class I Solar Carve-Out new renewable energy resources, Class I Solar Carve-Out II new renewable energy resources, Class II existing renewable energy resources and Class II Waste Energy existing renewable resources that meet the RPS requirements.� The companies are also seeking proposals for certificates that meet the APS, CPS, and CES-E requirements.� The following tables summarize the quantity of certificates the companies are seeking:
Year
MA RPS Qualified NEPOOL GIS Certificates(Class I)
MA RPS Qualified NEPOOL GIS Certificates (Class I Solar Carve-Out)
MA RPS Qualified NEPOOL GIS Certificates (Class I Solar Carve-Out II)
MA RPS Qualified NEPOOL GIS Certificates(Class II)
MA RPS Qualified NEPOOL GIS Certificates(Class II-Waste Energy)
MA APS Qualified NEPOOL GIS Certificates(AEC)
2023
0
6,000
18,000
15,000
15,000
20,000
2024
0
0
38,000
40,000
40,000
75,000
Year
MA CES Qualified NEPOOL GIS Certificates(CES-E)
MA CPS Qualified NEPOOL GIS Certificates (CPEC)
2023
250,000
50,000
2024
300,000
50,000
Respondent Proposal Information and Pricing Due
December 5, 2023 @
12pm EPT
Company Reviews Pricing and Informs Winning Respondents
December 7, 2023@
5pm EPT
Request for Proposal (pdf)
Contacts:
Kris Hornberger
Wholesale Electric Supply
National Grid [email protected]
(email)
Request For Renewable Energy Certificates
November 21, 2023
For Calendar Years:
Rhode Island
2023
The Narragansett Electric Company ("Narragansett") has issued a Request for Proposals to purchase Renewable Energy Certificates (RECs) to meet the Rhode Island Renewable Energy Standard (RES). Narragansett is seeking proposals for the supply of RECs from generating facilities in Rhode Island, New England and surrounding regions that have been approved by the Rhode Island Public Utilities Commission as existing renewable energy resources that meet the RES requirements. The following table summarizes the quantity of certificates Narragansett is seeking:
Year
NEPOOL-GIS Certificates from Existing Energy Resources
NEPOOL-GIS Certificates from New Energy Resources
Total NEPOOL-GIS Certificates
2023
30,000
0
30,000
-->
Respondent Information and Proposed Contract Modifications Due
November 27, 2023 @
5pm EST
Respondent Pricing Due
November 28, 2023
@ 10am EST
Request for Proposal (pdf)
Contacts:
Kris Hornberger
Wholesale Electric Supply
National Grid [email protected]
(email)
Request for Bids for Renewable Energy Certificates
November 13, 2023
For Vintage Year:
Massachusetts
2023
The Massachusetts Electric Company and Nantucket Electric Company ("Companies") have issued a Request for Bids for the sale of Class I Renewable Energy Certificates ("RECs") that meet the Massachusetts Renewable Energy Portfolio Standard ("RPS"). The following table summarizes the quantity of certificates and the state qualification held of the certificates that the Companies are seeking to sell:
Year
Quantity
MA RPS Qualified NEPOOL GIS Certificates (Class I)
Respondent Cover Letter and Bid Form Due
November 16, 2023, @
10am EST
Company Reviews Bids and Informs Winning Respondents
November 16, 2023 @ @
5pm EST
Request for proposal (pdf)
Contacts:
Kris Hornberger
Wholesale Electric Supply
National Grid [email protected]
(email)
Request for Bids for Renewable Energy Certificates
November 13, 2023
For Vintage Year:
Massachusetts
2023
The Massachusetts Electric Company and Nantucket Electric Company ("Companies") have issued a Request for Bids for the sale of Class I Renewable Energy Certificates ("RECs") that meet the Massachusetts Renewable Energy Portfolio Standard ("RPS"). The following table summarizes the quantity of certificates and the state qualification held of the certificates that the Companies are seeking to sell:
Year
Quantity
MA RPS Qualified NEPOOL GIS Certificates (Class I)
2023
135,000
Yes
Respondent Cover Letter and Bid Form Due
November 16, 2023, @
10am EST
Company Reviews Bids and Informs Winning Respondents
November 16, 2023 @ @
5pm EST
Request for proposal (pdf)
Contacts:
Kris Hornberger
Wholesale Electric Supply
National Grid [email protected]
(email)
Request For Power Supply Proposals
November 9, 2023
For the Periods:
Massachusetts
February 1, 2024 to January 31, 2025
The Massachusetts Electric Company and Nantucket Electric Company ("Companies") have issued a Request for Proposals to serve the following customer groups:
Massachusetts
Residential Customer Basic Service:
August 1, 2024 to January 31, 2025 (50% of load)
Massachusetts
Commercial Customer Basic Service:
August 1, 2024 to January 31, 2025 (50% of load)
Massachusetts
Industrial Customer Basic Service:
February 1, 2024 to April 30, 2024 (100% of load)
The Massachusetts Electric Company and Nantucket Electric Company ("Companies") have issued a Request for Proposals seeking fixed price bids for load following service for each of the customer groups in each of the three load zones (SEMA, NEMA, and WCMA). The Companies intend to evaluate and select supplier(s) on the same day that final pricing is due.
Respondent Proposal Information and Proposed Contract Modifications Due
November 22, 2023 @
5pm EPT
Indicative Pricing Due
December 6, 2023 @ 10am EPT
Final Pricing Due
December 13, 2023 @ 10am EPT
Request for Proposal (pdf)
Contacts:
James Calandra
Wholesale Electric Supply
National Grid
516.639.1359 [email protected]
(email)
James Ruebenacker
Wholesale Electric Supply
National Grid
516.545.3227 [email protected]
(email)
Request for Bids for Renewable Energy Certificates
October 16, 2023
For Calendar Year:
The Narragansett Electric Company
2023
The Narragansett Electric Company ("Narragansett") has issued a Request for Bids for the sale of Class I Renewable Energy Certificates ("RECs") that meet the Rhode Island Renewable Energy Standard ("RES"), the Massachusetts Renewable Energy Portfolio Standard ("RPS"), the Connecticut Renewable Portfolio Standard ("RPS") and the New Hampshire Renewable Portfolio Standard ("RPS"). The following table summarizes the quantity of certificates and the state qualifications held of the certificates that Narragansett is seeking to sell:
Year
Quantity
RI RES Qualified NEPOOL GIS Certificates (New)
MA RPS Qualified NEPOOL GIS Certificates (Class I)
<
CT Qualified NEPOOL GIS Certificates
Class I)
NH Qualified NEPOOL GIS Certificates
(Class I)
ME Qualified NEPOOL GIS Certificates
(Class I)
2023
77,000
Yes
Yes
Yes
Yes
No
-
Respondent Cover Letter and Bid Form Due
October 19, 2023, by
10am EPT
Company Reviews Bids and Informs Winning Respondents
October 19, 2023, by
5pm EPT
Request for Bids (pdf)
Contacts:
Kris Hornberger
Wholesale Electric Supply
National Grid [email protected]
(email)
Request For Power Supply Proposals
September 8, 2023
For the Periods:
Rhode Island
January 1, 2024 to September 30, 2024
The Narragansett Electric Company has issued a Request for Proposals to serve the following customer group(s):
Rhode Island
Last Resort Service Residential Customer Group:
April 1, 2024 to September 30, 2024 (20% of load)
Rhode Island
Last Resort Service Commercial Customer Group:
April 1, 2024 to September 30, 2024 (20% of load)
Rhode Island
Last Resort Service Industrial Customer Group:
January 1, 2024 to March 31, 2024 (100% of load)
In Rhode Island, The Narragansett Electric Company ("Narragansett") is seeking fixed price bids for load following service to meet its Last Resort Service for the Residential Group, the Commercial Group, and the Industrial Group. Narragansett intends to evaluate and select supplier(s) on the same day that final pricing is due. Narragansett reserves the right to award all or none of the blocks in the RFP.
Respondent Proposal Information Due
September 22, 2023 -
5pm EPT
Indicative Pricing Due
October 4, 2023 - 10am EPT
Final Pricing Due
October 11, 2023 - 10am EPT
Request for Proposal (pdf)
Request For Power Supply Proposals
August 11, 2023
For the Periods:
Massachusetts
November 1, 2023 to October 31, 2024
Massachusetts Electric Company and Nantucket Electric Company ("Companies") have issued a Request for Proposals to serve the following customer groups:
Massachusetts
Residential Customer Basic Service:
November 1, 2023 to October 31, 2024 (50% of load)
Massachusetts
Commercial Customer Basic Service:
November 1, 2023 to October 31, 2024 (50% of load)
Massachusetts
Industrial Customer Basic Service:
November 1, 2023 to January 31, 2024 (100% of load)
Massachusetts Electric Company and Nantucket Electric Company ("Companies") have issued a Request for Proposals seeking fixed price bids for load following service for each of the customer groups in each of the three load zones (SEMA, NEMA, and WCMA). The Companies intend to evaluate and select supplier(s) on the same day that final pricing is due.
Respondent Proposal Information Due
August 25, 2023 @
5pm EPT
Indicative Pricing Due
September 6, 2023 @ 10am EPT
Final Pricing Due
September 13, 2023 @ 10am EPT
Request for Proposal (pdf)
Request for Bids for Renewable Energy Certificates
August 10, 2023
For Calendar Year:
Massachusetts
2023
The Massachusetts Electric Company and Nantucket Electric Company ("Companies") have issued a Request for Bids for the sale of Class I Renewable Energy Certificates ("RECs") that meet the Massachusetts Renewable Energy Portfolio Standard ("RPS"). The following table summarizes the quantity of certificates and the state qualification held of the certificates that the Companies are seeking to sell:
Year
Quantity
MA RPS Qualified NEPOOL GIS Certificates(Class I)
2023
56,000
Yes
Respondent Cover Letter and Bid Form Due
August 15, 2023, by
10am EST
Company Reviews Bids and Informs Winning Respondents
August 15, 2023, by
5pm EST
Request for Bids (pdf)
Request For Power Supply Proposals
June 9, 2023
For the Periods:
Rhode Island
October 1, 2023 to March 31, 2025
The Narragansett Electric Company has issued a Request for Proposals to serve
the following customer group(s):
Rhode Island
Last Resort Service Residential Customer Group:
October 1, 2023 to March 31, 2025 (20% of load)
Rhode Island
Last Resort Service Commercial Customer Group:
October 1, 2023 to March 31, 2025 (20% of load)
Rhode Island
Last Resort Service Industrial Customer Group:
October 1, 2023 to December 31, 2023 (100% of load)
In Rhode Island, The Narragansett Electric Company ("Narragansett") is seeking fixed price bids for load following service to meet its Last Resort Service for the Residential Group, the Commercial Group, and the Industrial Group. Narragansett intends to evaluate and select supplier(s) on the same day that final pricing is due. Narragansett reserves the right to award all or none of the blocks in the RFP.
Respondent Proposal Information Due
June 23, 2023 -
5pm EPT
Indicative Pricing Due
July 5, 2023 - 10am EPT
Final Pricing Due
July 12, 2023 - 10am EPT
Request for Proposal (pdf)
Request For Power Supply Proposals
May 12, 2023
For the Periods:
Massachusetts
August 1, 2023 to October 31, 2023
Massachusetts Electric Company and Nantucket Electric Company ("Companies") have issued a Request for Proposals to serve the following customer group:
Massachusetts
Industrial Customer Basic Service:
August 1, 2023 to October 31, 2023 (100% of load)
Massachusetts Electric Company and Nantucket Electric Company ("Companies") have issued a Request for Proposals seeking fixed price bids for load following service for the Industrial Customer Group in each of the three load zones (SEMA, NEMA, and WCMA). The Companies intend to evaluate and select supplier(s) on the same day that final pricing is due.
Respondent Proposal Information and Proposed Contract Modifications Due
May 26, 2023 @
5pm EPT
Indicative Pricing Due
June 7, 2023 @
10am EPT
Final Pricing Due
June 14, 2023@
10am EPT
Request for Proposal (pdf)
Proposed Massachusetts Master Power Agreement (doc)
Required Proposal Information (doc)
Pricing Submission Form (xls)
Massachusetts
Electric Default Service - Load Data
Nantucket Electric Default Service -
Load Data
Massachusetts
Electric Load Estimation Files
Customer Count Data
Massachusetts Electric Rate Tariffs
Municipal Aggregation Data (xls)
ICAP Tags
Contacts:
Jim Calandra
Wholesale Electric Supply
National Grid
516.545.5433 [email protected]
(email)
Contacts:
James Ruebenacker
Wholesale Electric Supply
National Grid
516.545.3227 [email protected]
(email)
Request for Bids for Renewable Energy Certificates
July 24, 2023
For Calendar Year:
The Narragansett Electric Company
2023
The Narragansett Electric Company ("Narragansett") has issued a Request for Bids for the sale of Class I Renewable Energy Certificates ("RECs") that meet the Rhode Island Renewable Energy Standard ("RES"), the Massachusetts Renewable Energy Portfolio Standard ("RPS"), the Connecticut Renewable Portfolio Standard ("RPS") and the New Hampshire Renewable Portfolio Standard ("RPS"). The following table summarizes the quantity of certificates and the state qualifications held of the certificates that Narragansett is seeking to sell:
Year
Quantity
MA RPS Qualified NEPOOL GIS Certificates (New)
MA RPS Qualified NEPOOL GIS Certificates (Class I)
<
CT Qualified NEPOOL GIS Certificates (Class I)
NH Qualified NEPOOL GIS Certificates (Class I)
ME Qualified NEPOOL GIS Certificates (Class I)
2023
18,000
Yes
Yes
Yes
Yes
No
-
Respondent Cover Letter and Bid Form Due
July 26, 2023, by
10am EPT
Company Reviews Bids and Informs Winning Respondents
July 26, 2023, by @
5pm EPT
Request for Bids (pdf)
Proposed Master Certificate Sales Agreement (doc)
Bid Form (xls)
Contacts:
Kris Hornberger
Wholesale Electric Supply
National Grid
518.433.3359 [email protected]
(email)
Request For Proposals for Renewable Energy Certificates
May 3, 2023
For Calendar Years:
Massachusetts
2022 2023
The Massachusetts Electric Company and Nantucket Electric Company have issued a Request for Proposals to purchase Renewable Energy Certificates ("RECs") to meet the Massachusetts Renewable Energy Portfolio Standard ("RPS"), the Alternative Energy Portfolio Standard ("APS"), the Clean Peak Energy Portfolio Standard ("CPS") and the Clean Energy Standard ("CES"). The Massachusetts Electric Company and the Nantucket Electric Company are seeking proposals for the supply of certificates from generating facilities in Massachusetts, New England and surrounding regions that have been approved by the Massachusetts Department of Energy Resources as Class I new renewable energy resources, Class I Solar Carve-Out new renewable energy resources, Class I Solar Carve-Out II new renewable energy resources, Class II existing renewable energy resources and Class II Waste Energy existing renewable resources that meet the RPS requirements. The companies are also seeking proposals for certificates that meet the APS, CPS, and CES-E requirements. The following tables summarize the quantity of certificates the companies are seeking:
Year
MA RPS Qualified NEPOOL GIS Certificates(Class I)
MA RPS Qualified NEPOOL GIS Certificates (Class I Solar Carve-Out)
MA RPS Qualified NEPOOL GIS Certificates (Class I Solar Carve-Out II)
MA RPS Qualified NEPOOL GIS Certificates (Class II)
MA RPS Qualified NEPOOL GIS Certificates (Class II-Waste Energy)
MA APS Qualified NEPOOL GIS Certificates (AEC)
MA CES Qualified NEPOOL GIS Certificates (CES-E)
MA CPS Qualified NEPOOL GIS Certificates (CPEC)
2022
0
6000
20,000
5000
18,000
31,000
38,000
50,000
2023
0
10,000
40,000
40,000
30,000
35,000
300,000
50,000
Respondent Proposal Information and Pricing Due
May 9, 2023 @
12pm EPT
Company Reviews Pricing and Informs Winning Respondents
May 11, 2023 @
5pm EPT
Request for Proposal (pdf)
Request For Renewable Energy Certificates
April 25, 2023
For Calendar Years:
Rhode Island
2022 2023
The Narragansett Electric Company ("Narragansett") has issued a Request for Proposals to purchase Renewable Energy Certificates (RECs) to meet the Rhode Island Renewable Energy Standard (RES). Narragansett is seeking proposals for the supply of RECs from generating facilities in Rhode Island, New England and surrounding regions that have been approved by the Rhode Island Public Utilities Commission as existing renewable energy resources that meet the RES requirements. The following table summarizes the quantity of certificates Narragansett is seeking:
Year
NEPOOL-GIS Certificates from Existing Energy Resources
NEPOOL-GIS Certificates from New Energy Resources
Total NEPOOL-GIS Certificates
2022
6,881
0
6,881
2023
34,000
0
34,000
Respondent Proposal Information and Pricing Due
April 27, 2023 @
5pm EST
Company Reviews Pricing and Informs Winning Respondents
April 28, 2023
@
@ 10am EST
Request for Proposal (pdf)
Request For Power Supply Proposals
March 17, 2023
For the Periods:
Rhode Island
July 1, 2023 to September 30, 2024
The Narragansett Electric Company has issued a Request for Proposals to serve
the following customer group(s):
Rhode Island
Last Resort Service Residential Customer Group:
October 1, 2023 to September 30, 2024 (20% of load)
Rhode Island
Last Resort Service Commercial Customer Group:
October 1, 2023 to September 30, 2024 (20% of load)
Rhode Island
Last Resort Service Industrial Customer Group:
July 1, 2023 to September 30, 2023 (100% of load)
In Rhode Island, The Narragansett Electric Company ("Narragansett") is seeking fixed price bids for load following service to meet its Last Resort Service for the Residential Group, the Commercial Group, and the Industrial Group. Narragansett intends to evaluate and select supplier(s) on the same day that final pricing is due. Narragansett reserves the right to award all or none of the blocks in the RFP.
Respondent Proposal Information Due
March 31, 2023 -
5pm EPT
Indicative Pricing Due
April 20, 2023 - 11am EPT
Final Pricing Due
April 26, 2023 - 10am EPT
Request for Proposal (pdf)
Request For Proposals for Renewable Energy Certificates
February 27, 2023
For Calendar Years:
Massachusetts
2022 2023
The Massachusetts Electric Company and Nantucket Electric Company have issued a Request for Proposals to purchase certificates to meet the Massachusetts Renewable Energy Portfolio Standard ("RPS"), the Alternative Energy Portfolio Standard ("APS"), the Clean Peak Energy Portfolio Standard ("CPS") and the Clean Energy Standard ("CES"). The Massachusetts Electric Company and the Nantucket Electric Company are seeking proposals for the supply of certificates from generating facilities in Massachusetts, New England and surrounding regions that have been approved by the Massachusetts Department of Energy Resources as Class I new renewable energy resources, Class I Solar Carve-Out new renewable energy resources, Class I Solar Carve-Out II new renewable energy resources, Class II existing renewable energy resources and Class II Waste Energy existing renewable resources that meet the RPS requirements. The companies are also seeking proposals for certificates that meet the APS, CPS, and CES-E requirements. The following tables summarize the quantity of certificates the companies are seeking:
Year
MA RPS Qualified NEPOOL GIS Certificates(Class I)
MA RPS Qualified NEPOOL GIS Certificates (Class I Solar Carve-Out)
MA RPS Qualified NEPOOL GIS Certificates (Class I Solar Carve-Out II)
MA RPS Qualified NEPOOL GIS Certificates (Class II)
MA RPS Qualified NEPOOL GIS Certificates (Class II-Waste Energy)
MA APS Qualified NEPOOL GIS Certificates (AEC)
MA CES Qualified NEPOOL GIS Certificates (CES-E)
MA CPS Qualified NEPOOL GIS Certificates (CPEC)
2022
0
10,000
35,000
8,000
15,000
40,000
100,000
50,000
2023
0
8,000
40,000
40,000
30,000
40,000
250,000
50,000
Respondent Proposal Information and Pricing Due
March 3, 2023 @
12pm EPT
Company Reviews Pricing and Informs Winning Respondents
Massachusetts Electric Company and Nantucket Electric Company ("Companies"") have issued a Request for Proposals to serve the following customer groups:
Massachusetts
Residential Customer Basic Service:
May 1, 2023 to April 30, 2024 (50% of load)
Massachusetts
Commercial Customer Basic Service:
May 1, 2023 to April 30, 2024 (50% of load)
Massachusetts
Industrial Customer Basic Service:
May 1, 2023 to July 31, 2023 (100% of load)
Massachusetts Electric Company and Nantucket Electric Company ("Companies") have issued a Request for Proposals seeking fixed price bids for load following service for each of the customer groups in each of the three load zones (SEMA, NEMA, and WCMA). The Companies intend to evaluate and select supplier(s) on the same day that final pricing is due.
Respondent Proposal Information and Proposed Contract Modifications Due
February 17, 2023 @
5pm EPT
Indicative Pricing Due
March 1, 2023 @
10am EPT
Final Pricing Due
March 8, 2023 @
10am EPT
Request for Proposal (pdf)
Request For Proposals for Renewable Energy Certificates
February 27, 2023
For Calendar Years:
Massachusetts
2022 2023
The Massachusetts Electric Company and Nantucket Electric Company have issued a Request for Proposals to purchase certificates to meet the Massachusetts Renewable Energy Portfolio Standard ("RPS"), the Alternative Energy Portfolio Standard ("APS"), the Clean Peak Energy Portfolio Standard ("CPS") and the Clean Energy Standard ("CES"). The Massachusetts Electric Company and the Nantucket Electric Company are seeking proposals for the supply of certificates from generating facilities in Massachusetts, New England and surrounding regions that have been approved by the Massachusetts Department of Energy Resources as Class I new renewable energy resources, Class I Solar Carve-Out new renewable energy resources, Class I Solar Carve-Out II new renewable energy resources, Class II existing renewable energy resources and Class II Waste Energy existing renewable resources that meet the RPS requirements. The companies are also seeking proposals for certificates that meet the APS, CPS, and CES-E requirements. The following tables summarize the quantity of certificates the companies are seeking:
Year
MA RPS Qualified NEPOOL GIS Certificates(Class I)
MA RPS Qualified NEPOOL GIS Certificates (Class I Solar Carve-Out)
MA RPS Qualified NEPOOL GIS Certificates (Class I Solar Carve-Out II)
MA RPS Qualified NEPOOL GIS Certificates (Class II)
MA RPS Qualified NEPOOL GIS Certificates (Class II-Waste Energy)
MA APS Qualified NEPOOL GIS Certificates (AEC)
MA CES Qualified NEPOOL GIS Certificates (CES-E)
MA CPS Qualified NEPOOL GIS Certificates (CPEC)
2022
0
10,000
35,000
8,000
15,000
40,000
100,000
50,000
2023
0
8,000
40,000
40,000
30,000
40,000
250,000
50,000
Respondent Proposal Information and Pricing Due
March 3, 2023 @
12pm EPT
Company Reviews Pricing and Informs Winning Respondents
March 7, 2023 @
5pm EPT
Request for Proposal (pdf)
Request For Renewable Energy Certificates
February 13, 2023
For Calendar Year:
Rhode Island
2022
The Narragansett Electric Company ("Narragansett") has issued a Request for Proposals to purchase Renewable Energy Certificates (RECs) to meet the Rhode Island Renewable Energy Standard (RES). Narragansett is seeking proposals for the supply of RECs from generating facilities in Rhode Island, New England and surrounding regions that have been approved by the Rhode Island Public Utilities Commission as existing renewable energy resources that meet the RES requirements. The following table summarizes the quantity of certificates Narragansett is seeking:
Year
NEPOOL-GIS Certificates from Existing Energy Resources
NEPOOL-GIS Certificates from New Energy Resources
Total NEPOOL-GIS Certificates
2022
50,000
0
50,000
Respondent Cover Letter and Bid Form Due
February 16, 2023 @
5pm EST
Company Reviews Bids and Informs Winning Respondents
February 17, 2023 @ @
10am EST
Request for proposal (pdf)
Proposed Certificate Purchase Agreement (doc)
Appendix B - Required Proposal Information (doc)
Bidder Sheet (xlsx)
Contacts:
Kris Hornberger
Wholesale Electric Supply
National Grid [email protected]
(email)
Request for Bids for Renewable Energy Certificates
February 6, 2023
For Calendar Year:
Massachusetts
2022
The Massachusetts Electric Company and Nantucket Electric Company ("Companies") have issued a Request for Bids for the sale of Class I Renewable Energy Certificates ("RECs") that meet the Massachusetts Renewable Energy Portfolio Standard ("RPS"). The following table summarizes the quantity of certificates and the state qualification held of the certificates that the Companies are seeking to sell:
Year
Quantity
MA RPS Qualified NEPOOL GIS Certificates (Class I)
2022
115,000
Yes
Respondent Cover Letter and Bid Form Due
February 8, 2023, by
10am EPT
Company Reviews Bids and Informs Winning Respondents
February 8, 2023, by @
5pm EPT
Request for Bids (pdf)
Proposed Master Certificate Sales Agreement (doc)
Bid Form (xls)
Contacts:
Kris Hornberger
Wholesale Electric Supply
National Grid
518.433.3359 [email protected]
(email)
Request For Power Supply Proposals
December 22, 2022
For the Periods:
Rhode Island
April 1, 2023 to March 31, 2025
The Narragansett Electric Company has issued a Request for Proposals to serve the following customer group(s):
Rhode Island
Last Resort Service Residential Customer Group:
April 1, 2023 to March 31, 2025 (15% of load)
Rhode Island
Last Resort Service Commercial Customer Group:
April 1, 2023 to March 31, 2025 (15% of load)
Rhode Island
Last Resort Service Industrial Customer Group:
April 1, 2023 to June 30, 2023 (100% of load)
In Rhode Island, The Narragansett Electric Company ("Narragansett") is seeking fixed price bids for load following service to meet its Last Resort Service for the Residential Group, the Commercial Group, and the Industrial Group. Narragansett intends to evaluate and select supplier(s) on the same day that final pricing is due. Narragansett reserves the right to award all or none of the blocks in the RFP.
Respondent Proposal Information Due
December 29, 2022 @
5pm EPT
Indicative Pricing Due
January 4, 2023 @
10am EPT
Final Pricing Due
January 11, 2023 @
10am EPT
Request for Proposal (pdf)
Request For Proposals for Renewable Energy Certificates
November 29, 2022
For Calendar Years:
Massachusetts
2022 2023
The Massachusetts Electric Company and Nantucket Electric Company have issued a Request for Proposals to purchase Renewable Energy Certificates ("RECs") to meet the Massachusetts Renewable Energy Portfolio Standard ("RPS"), the Alternative Energy Portfolio Standard ("APS"), the Clean Peak Energy Portfolio Standard ("CPS") and the Clean Energy Standard ("CES"). The Massachusetts Electric Company and the Nantucket Electric Company are seeking proposals for the supply of certificates from generating facilities in Massachusetts, New England and surrounding regions that have been approved by the Massachusetts Department of Energy Resources as Class I new renewable energy resources, Class I Solar Carve-Out new renewable energy resources, Class I Solar Carve-Out II new renewable energy resources, Class II existing renewable energy resources and Class II Waste Energy existing renewable resources that meet the RPS requirements. The companies are also seeking proposals for certificates that meet the APS, CPS, and CES-E requirements. The following tables summarize the quantity of certificates the companies are seeking:
Year
MA RPS Qualified NEPOOL GIS Certificates(Class I)
MA RPS Qualified NEPOOL GIS Certificates (Class I Solar Carve-Out)
MA RPS Qualified NEPOOL GIS Certificates (Class I Solar Carve-Out II)
MA RPS Qualified NEPOOL GIS Certificates (Class II)
MA RPS Qualified NEPOOL GIS Certificates (Class II-Waste Energy)
MA APS Qualified NEPOOL GIS Certificates (AES)
MA CES Qualified NEPOOL GIS Certificates (CES-E)
MA CPS Qualified NEPOOL GIS Certificates (CPEC)
2021
0
10,000
40,000
10,000
20,000
40,000
100,000
75,000
2022
0
8,000
40,000
30,000
30,000
40,000
200,000
50,000
Respondent Proposal Information and Pricing Due
December 6, 2022 @
12pm EPT
Company Reviews Pricing and Informs Winning Respondents
December 8, 2022 @
by
5pm EPT
Request for Proposal (pdf)
Request For Power Supply Proposals
November 10, 2022
For the Periods:
Massachusetts
February 1, 2023 to October 31, 2023
Massachusetts Electric Company and Nantucket Electric Company ("Companies") have issued a Request for Proposals to serve the following customer groups:
Massachusetts Electric Company and Nantucket Electric Company ("Companies") have issued a Request for Proposals seeking fixed price bids for load following service in each of the three load zones (SEMA, NEMA, and WCMA). The Companies intend to evaluate and select supplier(s) on the same day that final pricing is due.
Respondent Proposal Information and Proposed Contract Modifications Due
November 23, 2022 @
5pm EPT
Indicative Pricing Due
December 7, 2022 @
10am EPT
Final Pricing Due
December 14, 2022 @
10am EPT
Request for Proposal (pdf)
Request for Bids for Renewable Energy Certificates
November 10, 2022
For Vintage Year:
Massachusetts
2022
The Massachusetts Electric Company and Nantucket Electric Company have issued a Request for Proposals to purchase certificates to meet the Massachusetts Renewable Energy Portfolio Standard (“RPS”), the Alternative Energy Portfolio Standard (“APS”), the Clean Peak Energy Portfolio Standard (“CPS”) and the Clean Energy Standard (“CES”). The Massachusetts Electric Company and the Nantucket Electric Company are seeking proposals for the supply of certificates from generating facilities in Massachusetts, New England and surrounding regions that have been approved by the Massachusetts Department of Energy Resources as Class I new renewable energy resources, Class I Solar Carve-Out new renewable energy resources, Class I Solar Carve-Out II new renewable energy resources, Class II existing renewable energy resources and Class II Waste Energy existing renewable resources that meet the RPS requirements. The companies are also seeking proposals for certificates that meet the APS, CPS, and CES-E requirements. The following tables summarize the quantity of certificates the companies are seeking:
Year
Quantity
MA RPS Qualified NEPOOL GIS Certificates (Class I)
2022
125,000
Yes
Respondent Cover Letter and Bid Form Due
November 15, 2022 @
10am EPT
Company Reviews Bids and Informs Winning Respondents
November 15, 2022
by
5pm EPT
Request for Bids (pdf)
Proposed Master Certificate Sales Agreement (doc)
Bid Form (Part 3) (xls)
Contacts:
Kris Hornberger
Wholesale Electric Supply
National Grid
518.433.3359 [email protected]
(email)
Request for Bids for Renewable Energy Certificates
October 24, 2022
For Vintage Year:
The Narragansett Electric Company
2022
The Narragansett Electric Company ("Narragansett") has issued a Request for Bids for the sale of Class I Renewable Energy Certificates ("RECs") that meet the Rhode Island Renewable Energy Standard ("RES"), the Massachusetts Renewable Energy Portfolio Standard ("RPS"), the Connecticut Renewable Portfolio Standard ("RPS") and the New Hampshire Renewable Portfolio Standard ("RPS"). The following table summarizes the quantity of certificates and the state qualifications held of the certificates that Narragansett is seeking to sell::
Year
Quantity
RI RES Qualified NEPOOL GIS Certificates (New)
MA RPS Qualified NEPOOL GIS Certificates (Class I)
CT Qualified NEPOOL GIS Certificates(Class I)
NH Qualified NEPOOL GIS Certificates(Class I)
ME Qualified NEPOOL GIS Certificates(Class I)
2022
76,000
Yes
Yes
Yes
Yes
No
Respondent Cover Letter and Bid Form Due
October 27, 2022 @ 10am EPT
Company Reviews Bids and Informs Winning Respondents
october 27, 2022, by 5pm EPT
Request for Bids (pdf)
Request For Power Supply Proposals
September 9, 2022
For the Periods:
Rhode Island
January 1,2023 to September 30,2023
The Narragansett Electric Company has issued a Request for Proposals to serve the following customer groups(s):
Rhode Island
Last Resort Service Residential Customer Group:
April 1, 2023 to September 30, 2023 (20% of load)
Rhode Island
Last Resort Service Commercial Customer Group:
April 1, 2023 to September 30, 2023 (20% of load)
Rhode Island
Last Resort Service Industrial Customer Group:
January 1, 2023 to March 31, 2023 (100% of load)
In Rhode Island, The Narragansett Electric Company("Narragansett") is seeking fixed price bids for load following service to meet its Last Resort Service for the Residential Group, the Commercial Group, and the Indrustrial Group. Narragansett intends to evaluate and select supplier(s) on the same day that final pricing is due. Narragansett reserves the right to award all or none of the blocks in the RFP
Respondent Proposal Information Due
September 23, 2022 @
5pm EPT
Indicative Pricing Due
October 5, 2022 @
10am EPT
Final Pricing Due
October 12, 2022 @
10am EPT
Request for Proposal (pdf)
Request For Power Supply Proposals
August 12, 2022
For the Periods:
Massachusetts
November 1, 2022 to october 31, 2023
Massachusetts Electric Company and Nantucket Electric Company ("Companies") have issued a Request for Proposals to serve the following customer groups:
Massachusetts
Residential Customer Basic Service:
November 1, 2022 to October 31, 2023 (50% of load)
Massachusetts
Commercial Customer Basic Service:
November 1, 2022 to October 31, 2023 (50% of load)
Massachusetts
Industrial Customer Basic Service:
November 1, 2022 to January 31, 2023 (100% of load)
Massachusetts Electric Company and Nantucket Electric Company ("Companies") have issued a Request for Proposals seeking fixed price bids for load following service for each of the customer groups in each of the three load zones (SEMA, NEMA, and WCMA). The Companies intend to evaluate and select supplier(s) on the same day that final pricing is due.
Respondent Proposal Information and Proposed Contract Modifications Due
August 26, 2022 @
5pm EPT
Indicative Pricing Due
September 7, 2022 @
10am EPT
Final Pricing Due
September 14, 2022 @
10am EPT
Request for Proposal (pdf)
Request for Bids for Renewable Energy Certificates
August 8, 2022
For Calendar Years:
Massachusetts
2022 2023
The Massachusetts Electric Company and Nantucket Electric Company have issued a Request for Proposals to purchase Renewable Energy Certificates ("RECs") to meet the Massachusetts Renewable Energy Portfolio Standard ("RPS"), the Alternative Energy Portfolio Standard ("APS"), the Clean Peak Energy Portfolio Standard ("CPS") and the Clean Energy Standard ("CES"). The Massachusetts Electric Company and the Nantucket Electric Company are seeking proposals for the supply of certificates from generating facilities in Massachusetts, New England and surrounding regions that have been approved by the Massachusetts Department of Energy Resources as Class I new renewable energy resources, Class I Solar Carve-Out new renewable energy resources, Class I Solar Carve-Out II new renewable energy resources, Class II existing renewable energy resources and Class II Waste Energy existing renewable resources that meet the RPS requirements. The companies are also seeking proposals for certificates that meet the APS, CPS, and CES-E requirements. The following tables summarize the quantity of certificates the companies are seeking
Year
MA RPS Qualified NEPOOL GIS Certificates (Class I)
MA RPS Qualified NEPOOL GIS Certificates (Class I Solar Carve-Out)
MA RPS Qualified NEPOOL GIS Certificates (Class I Solar Carve-Out II)
MA RPS Qualified NEPOOL GIS Certificates (Class II)
MA RPS Qualified NEPOOL GIS Certificates (Class II-Waste Energy)
MA APS Qualified NEPOOL GIS Certificates (AEC)
MA CES Qualified NEPOOL GIS Certificates (CES-E)
MA CPS Qualified NEPOOL GIS Certificates (CPEC)
2021
0
20,000
40,000
20,000
30,000
75,000
225,000
75,000
2022
0
10,000
30,000
40,000
40,000
75,000
225,000
25,000
Respondent Proposal Information and Pricing Due
August 15, 2022 @
12 pm EPT
Company Reviews Pricing and Informs Winning Respondents
August 17,2022 @ @
5pm EPT
Request for Proposal (pdf)
Request for Bids for Renewable Energy Certificates
July 26, 2022
For Vintage Year:
The Narragansett Electric Company
2022
The Narragansett Electric Company ("Narragansett") has issued a Request for Bids for the sale of Class I Renewable Energy Certificates ("RECs") that meet the Rhode Island Renewable Energy Standard ("RES"), the Massachusetts Renewable Energy Portfolio Standard ("RPS"), the Connecticut Renewable Portfolio Standard ("RPS") and the New Hampshire Renewable Portfolio Standard ("RPS"). The following table summarizes the quantity of certificates and the state qualifications held of the certificates that Narragansett is seeking to sell:
Year
Quantity
RI RES Qualified NEPOOL GIS Certificates (New)
MA RPS Qualified NEPOOL GIS Certificates (Class I)
CT Qualified NEPOOL GIS Certificates(Class I)
NH Qualified NEPOOL GIS Certificates(Class I)
ME Qualified NEPOOL GIS Certificates(Class I)
2022
23,000
Yes
Yes
Yes
Yes
No
Respondent Cover Letter and Bid Form Due
July 29, 2022 @
10am EPT
Company Reviews Bids and Informs Winning Respondents
July 29, 2022 @ @
5pm EPT
Request for Bids (pdf)
Request For Power Supply Proposals
June 10, 2022
For the Periods:
Rhode Island
October 1, 2022 to March 31, 2024
The Narragansett Electric Company has issued a Request for Proposals to serve
the following customer group(s):
Rhode Island
Last Resort Service Residential Customer Group:
October 1, 2022 to March 31, 2024 (20% of load)
Rhode Island
Last Resort Service Commercial Customer Group:
October 1, 2022 to March 31, 2024 (20% of load)
Rhode Island
Last Resort Service Industrial Customer Group:
October 1, 2022 to December 31, 2022 (100% of load)
In Rhode Island, The Narragansett Electric Company ("Narragansett") is seeking fixed price bids for load following service to meet its Last Resort Service for the Residential Group, the Commercial Group, and the Industrial Group. Narragansett intends to evaluate and select supplier(s) on the same day that final pricing is due. Narragansett reserves the right to award all or none of the blocks in the RFP.
Respondent Proposal Information Due
June 24, 2022 @
5pm EPT
Indicative Pricing Due
July 6, 2022 @ 10am EPT
Final Pricing Due
July 13, 2022 @ 10am EPT
Request for Proposal (pdf)
Request For Power Supply Proposals
May 6, 2022
For the Periods:
Massachusetts
August 1, 2022 to April 30, 2023
Massachusetts Electric Company and Nantucket Electric Company ("Companies") have issued a Request for Proposals to serve the following customer groups:
Massachusetts
Residential Customer Basic Service:
November 1, 2022 to April 30, 2023 (25% of load)
Massachusetts
Commercial Customer Basic Service:
November 1, 2022 to April 30, 2023 (50% of load)
Massachusetts
Industrial Customer Basic Service:
August 1, 2022 to October 31, 2022 (100% of load)
Massachusetts Electric Company and Nantucket Electric Company ("Companies") have issued a Request for Proposals seeking fixed price bids for load following service for each of the customer groups in each of the three load zones (SEMA, NEMA, and WCMA). The Companies intend to evaluate and select supplier(s) on the same day that final pricing is due.
Respondent Proposal Information and Proposed Contract Modifications Due
May 20, 2022 @
5pm EPT
Indicative Pricing Due
June 1, 2022 @
10am EPT
Final Pricing Due
June 8, 2022 @
10am EPT
Request for Proposal (pdf)
Request For Renewable Energy Certificates
May 2, 2022
For Calendar Years:
Massachusetts
2021 2022
The Massachusetts Electric Company and Nantucket Electric Company have issued a Request for Proposals to purchase Renewable Energy Certificates ("RECs") to meet the Massachusetts Renewable Energy Portfolio Standard ("RPS"), the Alternative Energy Portfolio Standard ("APS"), the Clean Peak Energy Portfolio Standard ("CPS") and the Clean Energy Standard ("CES"). The Massachusetts Electric Company and the Nantucket Electric Company are seeking proposals for the supply of certificates from generating facilities in Massachusetts, New England and surrounding regions that have been approved by the Massachusetts Department of Energy Resources as Class I new renewable energy resources, Class I Solar Carve-Out new renewable energy resources, Class I Solar Carve-Out II new renewable energy resources, Class II existing renewable energy resources and Class II Waste Energy existing renewable resources that meet the RPS requirements. The companies are also seeking proposals for certificates that meet the APS, CPS, and CES-E requirements. The following tables summarize the quantity of certificates the companies are seeking:
Year
MA RPS Qualified NEPOOL GIS Certificates (Class I)
MA RPS Qualified NEPOOL GIS Certificates (Class I Solar Carve-Out)
MA RPS Qualified NEPOOL GIS Certificates (Class I Solar Carve-Out II)
MA RPS Qualified NEPOOL GIS Certificates (Class II)
MA RPS Qualified NEPOOL GIS Certificates (Class II-Waste Energy)
MA APS Qualified NEPOOL GIS Certificates (APS)
MA CES Qualified NEPOOL GIS Certificates (CES-E)
MA CPS Qualified NEPOOL GIS Certificates (CPEC)
2021
0
5000
7000
14000
8000
13,000
45,000
25,000
2022
0
15,000
40,000
15,000
40,000
75,000
225,000
75,000
Respondent Proposal Information and Pricing Due
May 12, 2022 @
12pm EPT
Company Reviews Pricing and Informs Winning Respondents